ME 2&3 Overhauls for Survey | 6-8 weeks | 2 marine engineers, 2 fitters |
Bergen diesel overhaul | 2-3 weeks | 1 marine engineer, 2-3 motormen |
Overhaul ME pumps | 1-2 weeks | 1 marine engineer or 1 machinist |
Installing Chillers | 4-6 weeks | 1 fitter, 1 welder, 1 elctrician |
Installing Sewage systems | 3-4 weeks | 1 fitter, 1 welder, 1 electrician |
Dismantle Geny 1 | 1-2 weeks | 1 engineer, 1 motorman |
Installing Geny 1 piping (new) | 2-3 weeks | 1 fitter, 1 welder |
Building a bilge water circ. Tank | 1-2 weeks | 1 fitter, 1 welder |